CurbScape Installation Process
|
Step
1 Jobsite Prep: Our Truck! We take care of your lawn and lay tarps under the areas where we make the concrete. |
|
|---|---|---|
![]() |
Step 2 Trenching: We carefully cut a trench one to two inches deep, where the customer states they want the CurbScape. |
|
![]() |
Step 3 Cleaning the trench: We will than take all of the dirt that we have made and your existing plastic edging and dispose of appropriately. |
|
![]() |
Step 4 Mixing the concrete: Our special mix of concrete and additives is mixed on site to the color that is chosen by the customer. The ingredients of our mix are the keys to having the most beautiful and most durable CurbScaping on the market. |
|
![]() |
Step 5
Extruding the Curb: The concrete is shoveled into the curb machine and extruded into the trench. Our machine is one of the newest on the market. It has one of the best compaction rams available. Meaning: Strong curb. |
|
![]() |
Step 6 Finishing: Then all of our curb is then troweled carefully by hand and is adjusted if needed. |
|
![]() |
Step 7 Cutting/Stamping: We then do stamping of the curb if purchased. Following the stamping comes the cutting of control joints every two feet. This gives the curb flexibility for the freeze/ thaw cycle. |
|
![]() |
Step 8 Beautiful CurbScape: We would then seal the CurbScape to lock in the beauty and out the weather. There you have it, a painless process to get the nicest looking landscape border on the planet. |
|
|
||